Bridge over river Sava near Ostruznica - phase II

Mostprojekt finished main design of the bridge over river Sava with approach structures near Ostruznica (Belgrade) - left highway line (phase II).

Total length of the bridge is 1.963m, 14.3m wide consist of:

-approach structures on left bank – 591m
-steel structure over river Sava – 583m
-approach structure on right bank – 704m
-bridge over highway Belgrade – Obrenovac – 85m

Abutments and river piers are completed in whole profile in phase I

Approach structures on left bank consists of 3 continuous structures with precast prestressed girders 2.25m height. Spans ~11x30m and 5x40m

Steel structure over river Sava – 583m long. Main span 198m and 4 aside spans, 3x99+88m. Main steel bridge is made with varying-depth girder.3.5m - 7.96m

Approach structures on right bank 704 m long - consists of 4 continuous structures with precast prestressed girders 1.90m height. Spans ~21x30m

Bridge over highway Belgrade – Obrenovac – 85m long – continuous structure – 4 spans 17.5+3x25+17.5m. Cross section of structure, 1.16m height, is formed of 9 precast reinforced concrete girders 1.0m height, at 1.5m distance and deck 14.14m width and 16cm thick. Deck is casted on site over precast girders.

OSTR-001

OSTR-002